NASA Logo, National Aeronautics and Space Administration
SSO Small Explorers Acquistion.

SSO Small Explorers Acquistion.

Science Support Office: Explorers Acquisition

SMEX Phase A Additional Questions and Answers

Question 1: Does NASA require the CSR to demonstrate compatibility with both Pegasus XL and Falcon 1?
Answer: NASA requires that proposers stay within the performance parameters defined in the "ELV Launch Services Program Information Summary" document in the SMEX Library. Proposers must specify their launch service requirements as the minimum required to achieve the proposed mission. Dual compatibility is therefore achieved by defining the launch services requirements independent of a specific vehicle or provider. Proposers may reference Attachment 1 of the Information Summary for the type of requirements to include in the CSR.
Question 2: Will TMCıs evaluation of a mission include a requirement to be compatible with both Pegasus XL and Falcon 1?
Updated Answer for Clarification: The TMC's evaluation will verify the CSR requirements are consistent with launch services suitable for SMEX-class missions as described by the range of parameters in the "ELV Launch Services Program Information Summary." Therefore, the CSR should not reference a specific launch vehicle, but should specify the launch service requirements as the minimum required to achieve the proposed mission. Proposers may reference Attachment 1 of the Information Summary for the type of requirements to include in the CSR. As a part of the TMC evaluation, differences between baseline mission requirements and SMEX-class launch services capabilities across launch service providers will be noted, but not designated as a weakness.
Question 3: If compatibility with both Pegasus XL and Falcon 1 is not required for the CSR, will compatibility with both Pegasus XL and Falcon 1 be required for Phase B?
Answer: The requests for launch services proposals anticipated for Phase B are for a competitive procurement. Therefore, the launch services requirements for all missions are defined by identifying the minimum required to achieve the proposed mission without reference to a specific launch vehicle.
Question 4: Is compatibility demonstrated by showing positive mass margin to orbit performance and being able to fit within the payload fairing, or are other factors required such as launch loads, acoustics and mechanical/electrical interfaces to the launch vehicle?
Answer: Compatibility is achieved by defining the launch services requirements independent of a specific vehicle or provider, but consistent with the mission class as defined by the performance parameters in the "ELV Launch Services Program Information Summary" document in the SMEX library.
Question 5: Will NASA release an updated ELV Launch Services Program Information Summary with the appropriate technical and cost data for Falcon 1 so that a compatibility assessment can be made?
Answer: An updated ELV Launch Services Program Information Summary document will not be released. However, additional updated information on the launch services may be obtained by using the LSP performance tool (http://elvperf.ksc.nasa.gov) or contacting the LSP representative identified at the SMEX Phase A Kick-off meeting, Wanda Harding at wanda.j.harding@nasa.gov or at (321) 867-4968.
Question 6: What are the cost impacts, if any, of launching from different launch sites on the Falcon 1?
Answer: The CSR costs should remain consistent with the currently published guidelines. Proposers will not be responsible for incorporating unpublished numbers, nor should savings be assumed based on anticipated differences across potential providers.
Question 7: Are mass margins for Phase A required to meet GSFC Golden Rules requirements for both launch vehicles?
Answer: Provide only one mass margin for your proposal. You should use the terminology and definitions for Contingency (or reserve) and Margin as defined in appendix B of the AO. The evaluation will be based on the Guidelines and Criteria for the Phase A Concept Study and the AO requirements and constraints which do not state specific Technical Resource Margin requirements. The evaluation team will review your specific mission proposal and the proposed margins and determine whether the proposed reserves are sufficient and appropriate for your specific mission proposal. The GSFC Golden Rules document, GSFC-STD-10000 is listed in the SMEX library as a reference document and proposers should be aware of these GSFC "rules" in anticipation of being selected. Note that in the introduction to this document it says, "GSFC Rules are not intended to serve as a "cookbook" or "how-to" guide, but rather as another tool for assessing overall project risk and assuring mission success."
Question 8: To what level of detail we identify changes to section outside of the science implementation section is unclear. Need to clarify.
Updated Answer for Clarification: Section J Cost Proposal of the Guidelines and Criteria for the Phase A Concept Study, says that ³The contractor will be requested to submit a formal cost proposal based upon the Federal Acquisition Regulation (FAR) Part 15. The instruction and format for submission of this proposal are found in FAR Part 1 .403-5 and Table 15.2. It is essential that the cost elements proposed in the formal contract proposed to contract award be traceable to the cost proposal provided in the CSR. Any changes in cost from the Concept Study Report should be described in detail." This is not referring a change from the step one proposal.
 
However, in Technical Approach section 4 it says "Highlight any changes to the payload or individual instruments or their performance since submission of the proposal". Any thing that can affect the science that was proposed in the original proposal should be highlighted. If there are items that you are changing that can affect the science return of the mission that are described outside the science implementation section, we want you to "highlight" this in some way so we do not miss it. The level of detail is to describe what science would change and why you are making that change.
Question 9: Please verify that the SMEX that is downselected will immediately know that it was chosen for the first or second launch opportunity.
Answer: Yes, that is the intent. It is currently expected that this will be part of the selection decision and proposers will be notified whether they are the first or second launch when they are notified that they are selected.
Question 10: Even though the current CSR states that trade studies for NASA-provided services versus proposed alternatives could be conducted in Phase B, will the absence of the NASA services trade study affect the SMEX CSR evaluation?
Answer: Since we do not know what you are proposing until we receive your proposal, we cannot say in advance that there will be no effect.
Question 11: Is Microsoft Project a requirement or can another scheduling software be used (i.e. Primavera)?
Answer: Other software programs can be used for developing a schedule for your proposal. However, If you are using another software program for your schedule development, you should export your schedule in a format that is compatible with and can be read by Microsoft Project.
Question 12: What are the ground rules for the second selected mission?
Answer: The ground rules are described in section K of the Guidelines and Criteria for the Phase A Concept Study document. No further guidelines are known at this time. If you are selected for the second launch you may be asked to submit a revised funding profile based on information that is available at the time of selection.
Question 13: For the second launch, when will sufficient funding be available to start Phase C/D?
Answer: You should propose what you think is sufficient funding to start Phase C/D for the second launch date. If different information is available at the time of selection you may be asked to resubmit a funding profile after selection.
Question 14: For the second launch, does NASA have funding constraints? If so, what are they?
Answer: All known funding constraints will be stated in Section K.
Question 15: Is the Microsoft project version of the schedule an electronic version of the schedule submitted on a CD?
Answer: Yes.
Question 16: What level of detail do the evaluators wish to see in the Microsoft Project Schedule?
Answer: A project schedule page (a foldout is often used to allow details to be readable, but use of a foldout for this is up to the proposer and will count against the total limit for foldout pages) covering all phases of the investigation shall be provided. The schedule format shall have a timeline granularity of months or finer, have a corresponding table of dates, and follow standard NASA WBS elements for task descriptions as prescribed in NPR 7120.5D. The schedule page and accompanying narrative shall address proposed major milestones including, at a minimum, the following items:
- Instrument development and major review dates;
- Spacecraft development and major review dates;
- Instrument-to-spacecraft/host integration and test;
- Ground systems development and major review dates (e.g mission operations and data analysis development schedule);
- Major deliverables (e.g. ICDs, simulators, engineering modules, flight modules, etc.); and
- Launch vehicle integration and launch readiness;
- Long-lead item specifications, development paths, and their impacts to schedule;
- Development schedule for SEOs, if any;
- Schedule critical path identification; and
- Funded schedule reserve, with indications of appropriate reserves associated with major milestones and deliverables."
 
A electronic version of the schedule in a format readable by Microsoft project is required. As a guideline for this electronic schedule file, it is recommended that the schedule not exceed 2,000 lines with schedule detail down to component level. Components which have no development requirements (e.g. reaction wheels, power supplies) should be limited to a single line while components requiring development should have additional/appropriate detail which reflects the level of development.
Question 17: Is it a mandatory requirement to conduct cost trades (NASA vs. industry vs. university) for Communications, Tracking, Mission operations, Flight dynamics, and Data processing?
Answer: Section F.7 of the Guidelines and Criteria for the Phase A Concept Study says, "Contact with NASA-provided operations and communications services during the Concept Study is encouraged to better understand the options and associated costs.... Projects must conduct trade studies on the use of NASA-provided services versus any proposed alternatives."
Question 18: Since these cost trades are considered optional for Phase A, what is NASAıs criteria for conducting the trade during Phase A vs. Phase B?
Answer: There is no "criteria" for deciding when to conduct the trade study. NASA encourages proposers to do this in Phase A if they are proposing using non-NASA services in order to identify the true costs of these services prior to selection. Section F.7 of the Guidelines and Criteria for the Phase A Concept Study says, "Contact with NASA-provided operations and communications services during the Concept Study is encouraged to better understand the options and associated costs."
Question 19: In Part II, Paragraph 3 of the Guidelines and Criteria for the Phase A Study it says, "When changes have been made to any data provided with the original proposal as a result of the concept study, these changes from the proposal must be clearly identified." This requirement seems very broad; it is expected that there will be many updates and revisions to data in the original proposal as a result of the detailed work done in Phase A. Does this requirement apply outside Section E?
Answer: Yes. This is specifically addressed in section F.4 "Highlight any changes to the payload or individual instruments or their performance since submission of the proposal.
Question 20: In Part II, E, paragraph 1 of the Guidelines and Criteria for the Phase A Study it says, "changes to the science investigation section "should be highlighted in bold..". We have found that highlighting changes with column markings and blue text makes the changed sections obvious but more readable than bold text. Is this style acceptable?
Answer: Yes. The updated Guidelines and Criteria for the Phase A study will be updated to add "or color" to this requirement.
Question 21: What is the date for the second launch opportunity? This is needed to respond to Section K in the guideline document.
Answer: The second launch should be no earlier than April 2014 and no later than September 30, 2015.
Question 22: In regard to the section L of the CSR Guideline document, titled Justification and Cost Proposal for any SEO activities" it says that "Sufficient clarity in the CSR must exist to allow contractual execution if NASA downselects the mission or mission of opportunity and elects to include either or all of these additions." What specific types of information does NASA require?
Answer: In order to put contracts in place, NASA requires the level of information described in the Guidelines and Criteria for the Phase A Concept Study, Section J, Cost Proposal.
Question 23: Is the proposing team responsible for conducting the trade studies with NASA support, or is it NASA's responsibility to conduct the trade studies with the proposing team support?
Answer: It is the proposal team responsibility to conduct trade studies with NASA support. The NASA personnel that can assist in the trade studies are listed as points of contact the Mission Operations and Communications Services document.
Question 24: Part II, F, 4. "Highlight any changes to the payload or individual instruments or their performance since submission of the proposal." Does "highlight" have the same meaning as in Section E? Since most of Section F must be new, the same approach seems inappropriate.
Answer: Yes, you are correct that most of Section F is new and so Highlighting changes in the same way as required for the Section E may not feasible. You may choose how you would like to "highlight" these significant changes in section F "to the payload or individual instruments or their performance since submission of the proposal". Changes affecting science, should also be included in the science change matrix.
Question 25: Part II, J, paragraph 3. What is the anticipated schedule for the request of a formal cost proposal?
Answer: As described in the Cost Plan section, detailed cost data is required for Phase B as part of the Concept Study Report. Immediately after downselection, the formal cost and pricing data will be requested for all mission phases.
Question 26: Part II, M, appendix 1. There seems to be no requirement for Co-Investigator letters of commitment, except for contributed effort. Is this intentional?
Answer: A letter of commitment is required for all Co-Is as stated in AO section 4.5.4. This will be clarified in the Guidelines and Criteria for the Phase A study by updating section M.1.
Question 27: Page B-6, 4th Paragraph. Do we include the optional Student Collaborations (SC) and Science Enhancements Options (SEO) in the funding amounts included in the "Subcontracting Plan" ?
Answer: It depends on how proposers implement SC and SEO. If the proposer uses subcontracting as described under AO section 4.9 and AO Appendix A Section XIII to accomplish the SEO and or SC then they should include the funding amounts in the Subcontracting plan.
Question 28: Page B-6, Student Collaborations. Do we assume all SCıs originally proposed are still in contention?
Answer: Yes. You may keep the original SC if so desired.
Question 29: Page B-9, Item M-4. What are the "contract options"? I would assume Phases A, B, C/D, E, and F. Are the SC's and SEO's separate "options"?
Answer: SEOs and SCs can be addressed in appendix M.4 but must be addressed separately from the baseline mission since they may not be selected. Note that SCs are within the PI Mission cost cap but SEOs are not.
Question 30: Page B-9, Item M-15. Does the requested "Subcontracting Plan" refer to the total program (~$100M), or just the Bridge Phase/Phase B contract (<$25M)?
Answer: The subcontracting plan should address all phases of the investigation and the total PI mission cost.
Question 31: Page B-23, Table 1. Do we assume the proposed SC's are funded in completing Table 1?
Answer: The SC cost should be included in upper half of the chart that includes all PI Mission Costs.
Question 32: Page B-23, Table 2. Since the SEO's are treated separately in Table 7, are we to ignore them in Tables 1-6?
Answer: SEOs should also be listed at the bottom of Table 3.
Question 33: Could NASA provide some direction as to how a project can add a Co-I to the existing project team? This addition might be necessary to correct a major or minor weakness in the original proposal detected by NASA. It is also possible that a key scientist in the field was part of a competing proposal in the same field and is now available to join a selected proposal team.
Answer: You may add or change Co-Is during the Phase A study. Letters of Commitment are required for new Co-Is but this is no different than the other Co-Is.
Question 34: Pg B-11 Paragraph A. COVER PAGE. Please define "all participants". How far down into the organizations do we go? We are assuming that this is limited to PI, PM and all key personnel listed in Section G ­ Management.
Answer: All participants means all known participants at this time. This means the PI, PM, all Key personnel, all Co-Is and all participating organizations or institutions.
Question 35: Pg B-19 Paragraph G ­ 1.b.i and ii Principal Investigator and Project Manager ­ Does the requirement for a POC refer to one within the person's institution to verify role, responsibility, time commitment and experience or one from a customer to verify past performance?
Answer: The POC should be a person to verify past role and performance.
Question 36: How are the Science Requirements typically written for a PI-led mission of this scope?
Answer: An example is provided in the SMEX Library. See the document titled "Example: Project Level Requirements" in section 6 of the library.
Question 37: The cost proposal may be submitted in a separate volume. What should be included in the separate cost volume?
Answer: See Section J titled Cost Proposal for guidance.
Question 38: Three-ring binders may be used. Are binders preferred?
Answer: No.
Question 39: A Microsoft project version of the schedule is also to be provided. Each CD that will accompany the original or a copy of the CSR must include the required files. These CDs and the files in them must be compatible with both PCs and Macs. Clarification: MS Project does not make MS Project for the Mac.
Answer: Mac makes computers with the Intel chip which allows us to run the Windows operating system with software called Parallels. This allows us to run Microsoft Project on a Mac.
Question 40: A firm letter of commitment from international partners must be provided no later than the site visit. Question: Does anything for international partners need to be turned in at submittal?
Answer: NASA encourages you to provide the letters of commitment from international partners when you submit your CSR. If this is not possible then it may be as late as the site visit.
Question 41: The Bridge Phase Plan should include a detailed schedule and define the products to be delivered and the schedule for their delivery. Question: Does this need to be included as a separate MS project file on the CD?
Answer: No, it does not need to be a separate file.
Question 42: Are the any page limits on the Resumes?
Answer: Per the AO and updated Guideline document, "Resumes or curriculum vitae should be no longer than three pages for the PI and one page for each additional participant."
Question 43: What are the center of mass constraints and accuracy requirements?
Answer: The information captured in section 5.4.1 of the Pegasus Userıs Guide (PUG) Release 6.0 and section 3.1 of the Falcon Userıs Guide (FUG) Revision 7 may be used as references for the center of mass constraints and accuracy requirements.
Question 44: Are there any stiffness requirements for the LV payload?
Answer: Stiffness is more of a guideline than a requirement. The flight system's fundamental lateral frequency should be greater than 20 Hz to avoid dynamic coupling. A more conservative approach is the recommendation that both the fundamental axial and lateral be greater than 25 Hz. Additional guidelines will be provided upon launch vehicle selection in Phase B.
Question 45: Boeing uses the 5-100 Hz sine sweep as a flight dynamics dress rehearsal, while Orbital uses a payload random vibration. Do we know what SpaceX uses?
Answer: SpaceX recommends deriving a payload-peculiar sine vibe environment curve based upon a coupled loads analysis, updated with appropriate flight history.
Question 46: In the AO evaluation form, how will the evaluator rate our CSR for "Proposed LV Configuration" if we don't actually propose one?
Answer: The item "Proposed LV Configuration" pre-dates the expanded availability of launch services for SMEX-class missions. Therefore, the proposer may leave this item blank.
Question 47: If the Science Section will not be re-evaluated, but weaknesses become strengths and/or we show a stronger science   in the CSR , can we be moved from a Category 2 to a Category 1?
Answer: NASA will not categorize the CSR ­ that process was only for the Step 1 selection.  The science section will only be re-evaluated if there is a SIGNIFICANT change in the science.  The added implication of that is that the science implementation and TMC reviews will be for this new science you propose.
Question 48: If a Science Implementation foldout is currently in the Science Section, can it be removed and put in the Technical Section?   Can we start from scratch on the foldouts, even if they were in the Science Section? Can 6.a and 6.b (6. Science Implementation a.Instrumentation and b.Mission Concept) from the Pre-Phase A Proposal be moved from the Science Investigation to Section F in the Concept Study Report?
Answer: Yes. The proposer may reorganize and update the information from the original proposals as they wish but they must stay within the page limits and content descriptions of sections as defined in the Guidelines and Criteria for the Phase A study or the Science Investigation, Section E and Technical Approach, Section F.
Question 49: Is a Science Requirements Document due with the CSR? It's not listed in the Appendices, but neither is the PAIP, which is due with the CSR.
Answer: As described in the Guidelines document in section F.4 "The draft Level 1 science requirements of the investigation, as agreed to by the PI, PM and other key personnel, must be clearly identified in this section." Also, the appendix M.5 titled "Mission Definition and Requirements Agreement" is required and does include the Science Requirements.  An example of this document is in the SMEX library in section  6.  In regard to the PAIP, this document is not required as part of the CSR.  This document must be provided immediately after selection is announced which is currently in the Spring of 2009.
Question 50: Are cost still to be submitted in 08 dollars?
Answer: Yes. The cost cap for SMEX full mission investigations is $105 Million in Fiscal Year 2008 dollars. Follow the instructions in each cost table to show totals in Real Year and FY08 dollars.
Question 51: Is Table 2 to be prepared just for Phase B (as specified in the first sentence of the 4th paragraph on page B-25), or for 'each phase of the work' (as specified in the last sentence of the same paragraph)? What WBS elements are to be used for the rows? The text says to "use only the line items shown in Table 2 that are relevant...", but the example doesn't list all the elements and does not follow the structure specified in NPR 7120, so it is not obvious exactly what is required. Since the lines must add to the contract total, it would seem that all Level 2 elements are to called out separately, and Level 3 for the spacecraft (and Payload?). Is Table 2 limited to one page (as specified in the text)? If one includes all the required WBS elements, it cannot be put onto one page and stay within the font limitations.
Answer: Table 2 is intended to cover Phase B only. The WBS should be consistent with 7120.5D and go to level 2 for all elements and level 3 for the spacecraft & payload. Note that in the first paragraph of Part II ­ Required Quantities, Media, Format, and Content, cost tables are required to be submitted on the CD as separate excel files. "Proposers must also submit the data in cost tables as separate Microsoft Excel files." Also note that that as stated in the fourth paragraph, "Additional foldout pages may be used for the cost tables required in Sections J through L." Also note that there is no page limit on the cost section. If your table 2 does not fit on one page while meeting our font limits, consider using a foldout.
Question 52: Is there a process for changing key personnel from what was in the proposal to the CSR?
Answer: If the change is desired at the end of Phase A, just put it in the CSR. Approval of the CSR is approval for the change.
 
If the proposers wants to make a change to key personnel now, then they need to send a request to NASA now. It should be a letter through proper channels at the requesting organization, addressed to Dr. Hashima Hasan as Program Scientist. Tell us what you are doing, why, and include a 1 page CV for the new personnel.
 
The Evaluation Panel will review all key personnel as part of the evaluation process.
 
A definition of key personnel is in section 4.5.2 of the AO.
 
"In section 4.5.2 of the AO it is stated that "Any replacement of key personnel (including but not limited to the PI, PM, deputy PI, deputy PM, industry lead, and instrument leads) requires concurrence by NASA. Furthermore, the PM must be approved at each transition to the next phase..."
 
Note that Co-Is are not usually key (management) personnel. Changing Co-Is is proposed in the CSR and is approved at downselect. The proposer must explain what changes were made and why, since the Co-I list was part of the science evaluation. NASA will look at the new CO-I list and determine whether this warrants a new science peer review.
Question 53: Is it acceptable to change the order of material within section G or other sections in the Guidelines and Criteria for the Phase A Concept Study?
Answer: Yes.
Question 54: In regard to Appendix 19 ­ Is Bridge Phase the first 4 months of Phase B? Is that the separate cost proposal? (not the Bridge Phase and Phase B)
Answer: The requirement for Cost or Pricing data for the Bridge Phase and Phase B is stated in Section J.1. The last sentence of J.1.a specifically says that the data may be provided as Appendix M.19. Please carefully review section J.1 titled Cost Proposal for Bridge Phase and Phase B.
 
Also, note that the bridge phase is defined in the second sentence of Section J. " The bridge phase is intended to cover a four month period of Phase B effort to provide program continuity while the Phase B/C/D/E/F negotiations are completed."
Question 55: Appendix M-19 asks for Phase B cost and pricing data. Does this apply to PI institution only, the Prime contract or to all the organizations over $650K?
Answer: as described in section J.1.f.iii, all subcontractor costs need to be addressed.
Question 56: In addition to the prime contractor, do all subcontractors with a value of over $500K need to submit a Small Disadvantage Business Subcontracting Plan?
Answer: Appendix M.15 in the Concept Study Report is titled "Subcontracting Plan". This appendix needs to address all the subcontracting for the entire value of the investigation.
Question 57: Part II section E. Science Investigation, last sentence of first paragraph which starts, "If there are no changes,...". As we read this sentence it implies that if there are no changes to the section that you want the unchanged section included in Appendix M.17 with an affirmative statement in the appendix stating that there is no change to that section. Is that a correct interpretation of this sentence?
Answer: No, that is not the correct interpretation. "If there are no changes" (to your original science investigation in the proposal to the AO), "this section" (your original science investigation in the proposal to the AO) must be repeated identically from the proposal" (and put in section E of the Concept Study Report ­ not appendix M.17)" with a statement that there are no changes."
 
You only need to provide a science change matrix in Appendix M.17 if you have made changes.
 
"In addition, a change matrix giving the original (proposed) requirement, the new requirement, rationale for the change, and its location within the CSR is required as an appendix (see Section M.17)."
Question 58: Part II section A Cover Page and Investigation Summary. The first sentence states that "A cover page and summary must be part of the proposal,...It must be signed by the PI.....". Do you require the Color cover page to be signed or is it acceptable to have a custom page inserted behind the color cover page with the signatures and other detailed information as outlined in this section?
Answer: Yes it is acceptable to have a custom page inserted behind the color cover page with the signatures and other detailed information.
Question 59: Can proposers contact the GSFC Rapid Spacecraft Development Office (RSDO) to discuss the reasonableness of procuring a spacecraft bus through RSDO?
Answer: Yes. Proposers may contact the GSFC RSDO. Using RSDO is mentioned as a possibility in the AO in Appendix B.
 
"If the proposed spacecraft bus is in the Rapid Spacecraft Development Office catalog, explain how any changes to the technical specifications given in the catalog are going to be achieved and how those changes affect other subsystems."
 
The RSDO point-of-contact at GSFC is Gregory Smith (gregory.f.smith@nasa.gov)
Question 60: Regarding Appendix 4 - Statements of Work for each Contract Option - If a NASA center is a partnering organization on a SMEX, is a draft SOW required from that NASA Center? Or are the SOWs only needed for non-government partners.
Answer: The first sentence of Appendix 4 says "Provide draft Statement(s) of Work for all potential contracts with NASA". So, no this does not apply to NASA centers since NASA does not put contracts in place with NASA centers.
Question 61: The SMEX MAR has been a subject of conversation in regards to its defined responsibilities. It is written in such a way that it appears that GSFC has both the project and program level roles. Should we assume that the Proposer's Mission is the Project and as such is responsible for the deliverables that are stated in the MAR as well as other Project level roles. Also,the Proposerıs mission Project will provide updates to the GSFC Program Office, request expertise help as needed and invite GSFC to all significant reviews.
Answer: Yes: "that the Proposers Mission Project is responsible for the deliverables that are stated in the MAR as well as other Project level roles"... and that ... "they will provide updates to the GSFC Program Office, request expertise help as needed and invite GSFC to all significant reviews".
Question 62: Appendix M.5 of the CSR instructions requests a draft Mission Definition and Requirements Agreement. The IBEX example of the Mission Definition and Requirements document provided in the SMEX library includes a lot of detail. Is all that detail necessary at this stage?
Answer: Only a draft in requested. Provide details that reflected your Phase A Concept Study Report.
Question 63: In regard to E/PO, Is it true that NASA either requires or highly suggests a NASA review of the EPO program after Phase A, something akin to the Preliminary Design Review and the Critical Design Review? In reviewing the relevant documents (the AO and the EPO Evaluation Factors), I did not see anything suggesting that was the case, but I think it may be possible that I missed it. Is there such a requirement, or if not a requirement, is there is a suggested procedure for formal NASA reviews of the EPO program beyond the reports we will submit from our external evaluator?
Answer: An E/PO plan is a required element at CDR. NASA would like to see a good draft by PDR and will convene a small review team to provide comments on it. The E/PO plan is concurred on at HQ by the SMD E/PO Lead.
Question 64: An Integrated Baseline Review (generally 90 days after ATP) is required by EVM doctrine. This is a major review but is not called out in the SMEX AO as a program review milestone. Will it be required for this program by the SMD office?
Answer: The IBR review is related to the EVM process for which we have submitted a waiver to 7120.5D exempting Universities and Class D missions from the EVM requirement. Unfortunately, the waiver has not, at this time, been approved. That said, however, the IBR should be regarded as a detailed schedule review that should take place as part of the PDR and confirmation assessment review process or right after confirmation. Since the waiver has not yet been granted, the missions should plan to conduct this review.

 

 


 

 

+ Concept Study Home

ADDITIONAL Q&As