Kickoff Meeting Questions and Answers

Question 1: Do we need to get letters of commitment re-signed?
Answer: No, not if the work described in the original letter has not changed.
Question 2: Is the relevant experience and past performance appendices page count unlimited?
Answer: Yes
Question 3: Will you tell us the major issues coming out of the Initial Plenary?
Answer: Yes, this information is conveyed to you in the form of the questions we will send you prior to the site visit.
Question 4: What is the date for the second launch opportunity? This is needed to respond to Section K in the guideline document.
Answer: The second launch should be no earlier than April 2014 and no later than September 30, 2015.

 

 


 

 